Planned HVAC maintenance for 100+ cooling units at a Jeddah packaging plant

  • Metal packaging
  • Jeddah

Results

HVAC units on Glorek’s maintenance register
100+
full planned maintenance rounds (December 2025, April 2026)
2
HVAC work orders handled (December 2025 – September 2026)
9
consecutive months of operational manpower at the plant
41
Technician performing HVAC system diagnostics using digital measurement tools

Challenge

A metal packaging manufacturer with a factory in Jeddah, working with Glorek since 2022 under an operations and maintenance (O&M) contract.

The plant relies on more than 100 HVAC units – split units, window units and cooling towers – that all need regular servicing, and a record of what was done to each one.

What we did

Glorek registered every unit in its maintenance system as a separate asset, so each service is logged against the unit it was done on.

Planned maintenance runs as complete rounds under a work order: rounds ran in December 2025 and April 2026, and in the April round every unit on the register was serviced, with every task marked complete. Further HVAC requests are handled through the same system – 9 HVAC work orders between December 2025 and September 2026, with technician inspection records.

Alongside the maintenance, Glorek’s operational manpower team has worked at the plant every month since April 2023.

Result

One provider for both the plant’s operational manpower and its cooling equipment, with every HVAC unit on record and a full planned round completed on every unit.